Look Up!


The building has left the ground! On Wednesday they started piecing the building together and at 7:30 this morning they lifted the first roof section into place - praise God!

Wednesday, August 20, 2008

Rock wall for the sign


Pouring the Footings!

On Friday August 1 and Saturday August 2, several volunteers from LCC worked side by side to accomplish preparing the trenches, holes and rebar as well as pouring the cement for the footings. It was an awesome feeling known that we are gaining ground in the project.

Footings


Wednesday, May 21, 2008

The parking lot is being poured!

The north parking lot is transforming from a pile of dirt to a cement slab right before our eyes. It is great to see the tremendous progress taking place. The north parking will be poured over a period of about one week. The pad for the building still needs to be raised a few feet and then the footings can be poured. These are exciting days! Keep praying that God will be glorified through the process of building His ministry center.



Wednesday, May 14, 2008

The building is on site!

The building package arrived Monday, May 12th @ 8 am. As soon as the pad is finished for the building, footings will be poured and then the slab and then the building will be erected. What a day that will be. Praise God for His continued faithfulness and timetable.

Wednesday, April 30, 2008

Mountains are moving once again!

The land is beginning to take shape (literally)! If you haven't taken a trip past the land recently I encourage you to do so. While there is still a lot of dirt that has to be moved it looks totally different. God is back in action!